Plans

Proposed, funded, under construction, shelved. Each with its status, its date, and its money as the sources give it.

12plans
657billion baht, summed as published
2under construction
6under study
Planstatusmillion bahtkmdueas of
Four-laning Route 118 to Chiang Raibuilding2,00017.47320262026
San Klang interchangebuilding1,42520272025
Five interchanges on the outer ringfunded3,14520272025
The new comprehensive plan, 2026funded2026-03
The nine roads, 2025–27funded20272025
Chiang Mai–Chiang Rai motorway, MR1-3study101,1741842025
Lanna Airport, the second airport at Ban Thistudy70,00020322025
Chiang Mai light rail, the Red Linestudy27,00015.82032-122026-04
Ring 4, drawn but not dugstudy5,000502025
An elevated road on the outer ring, Don Kaew to Mueang Kaewstudy2,00020.8572025
The UNESCO nomination and the roads under itstudy2026-01
Bangkok–Chiang Mai high-speed railshelved445,3036682033–42 (phase 2 target)2024-10
Bangkok–Chiang Mai high-speed…445,303 mChiang Mai–Chiang Rai…101,174 mLanna Airport, the second…70,000 mChiang Mai light rail, the…27,000 mRing 4, drawn but not dug5,000 mFive interchanges on the…3,145 mAn elevated road on the outer…2,000 mFour-laning Route 118 to…2,000 mSan Klang interchange1,425 m
Status

Half of these have moved their date at least once

The light rail has three published lengths and four opening years. A plan is a rumour until someone puts money against it, and the table says which ones have.

The Red Line
This Photo was taken by Supanut Arunoprayote. Feel free to use any of my images, but please mention me as the author and may send me a message. (สามารถใช้ภาพได้อิสระ แต่กรุณาใส่เครดิตผู้ถ่ายและอาจส่ · CC BY 4.0

The new comprehensive plan, 2026

ผังเมืองรวมเมืองเชียงใหม่ ฉบับใหม่ 2569

The cabinet approved the draft on 17 March 2026: 1,428.90 km² over Mueang, San Sai, Mae Rim, Hang Dong, Saraphi and parts of Doi Saket and San…

fundedconstruction

An elevated road on the outer ring, Don Kaew to Mueang Kaew

ทางยกระดับบนทางหลวง 121 ดอนแก้ว–เมืองแก้ว

The highway department, not the expressway authority, studied six models from March 2025 for an elevated road on the west side of Route 121, 20.857…

studyconstruction

Bangkok–Chiang Mai high-speed rail

รถไฟความเร็วสูงกรุงเทพฯ–เชียงใหม่

The northern Shinkansen line: Bangkok–Phitsanulok 380 km, Phitsanulok–Chiang Mai 288 km, 668 km in all (688 by Isranews), 445,303 million baht for…

shelvedconstruction

Lanna Airport, the second airport at Ban Thi

This Photo was taken by Supanut Arunoprayote. Feel free to use any of my images, but please mention me as the author and may send me a message. (สามารถใช้ภาพได้อิสระ แต่กรุณาใส่เครดิตผู้ถ่ายและอาจส่ · CC BY 4.0

สนามบินล้านนา สนามบินแห่งที่สองที่บ้านธิ

A second airport across the provincial line at Ban Thi, Lamphun, beside San Kamphaeng: about 8,050 rai, about 70,000 million baht, 24 million…

studyconstruction

Chiang Mai light rail, the Red Line

CEphoto, Uwe Aranas · CC BY-SA 4.0

รถไฟฟ้าเชียงใหม่ สายสีแดง

Nakhon Ping Hospital to Mae Hia Saman Samakkhi. The MRTA's Thai page gives 15.8 km, 16 stations, seven underground, about 27,000 million baht; its…

studyconstruction

Chiang Mai–Chiang Rai motorway, MR1-3

มอเตอร์เวย์เชียงใหม่–เชียงราย MR1-3

An intercity motorway from Saraphi to Wiang Chai under the MR-MAP plan, three alignments of 178 to 217 km put to hearing on 20 September 2022. The…

studyconstruction

The nine roads, 2025–27

เก้าสายทาง 2568–70

Announced on provincial radio: Route 116 Lamphun–Doi Lo to four lanes; Route 108 Chom Thong–Hot to four lanes; Hot–Mae Sariang; Route 1095 Mae…

fundedconstruction

Five interchanges on the outer ring

ทางแยกต่างระดับห้าแห่งบนวงแหวนรอบนอก

Tendered as a set: Samoeng at Route 108 in Hang Dong, 920 million; the Superhighway at Route 11, 700 million; Louis at Route 1006, 650 million, a…

fundedconstruction

Four-laning Route 118 to Chiang Rai

ขยายทางหลวง 118 เป็นสี่เลนถึงเชียงราย

The whole 158.473 km to be four lanes. Done: Chiang Mai–Doi Saket 20.2 km, October 2008; Pong Pha Tong–Ban Pong 28.5 km, October 2019; Pa Miang–Pang…

buildingconstruction

The UNESCO nomination and the roads under it

Hartmann Linge · CC BY-SA 4.0

การเสนอมรดกโลกและถนนใต้มัน

Chiang Mai went on the tentative list in 2015 as Monuments, Sites and Cultural Landscape of Chiang Mai, Capital of Lanna: a nominated core of the old…

studyconstruction

Ring 4, drawn but not dug

Ssuri · CC BY-SA 3.0

วงแหวนรอบที่ 4

A fourth ring of about 50 km through Hang Dong, Saraphi, San Kamphaeng, Doi Saket, San Sai and Mae Rim, costed at about 5,000 million baht, at the…

studyconstruction

San Klang interchange

ทางแยกต่างระดับสันกลาง

Route 1317 across Route 121, east of the city. Thai PBS reported it more than half built in 2025 at 1,425 million baht; a second phase of 430 million…

buildingconstruction